The entire project is 66% complete, while the
        
        
          tunnels are more than 86% complete. The
        
        
          open sections of the motorway are almost 33%
        
        
          complete, as the necessary expropriations
        
        
          have not been finalized, leading to inevitable
        
        
          delays.
        
        
          2) The Elefsis-Corinth-Patra-Tsakona axis of
        
        
          Olympia Odos is scaled back, and a large part
        
        
          will be constructed later.
        
        
          Construction work –prior to the shutdown– on
        
        
          the new sections of the Corinth-Patras high-
        
        
          way focused on large structures, such as tun-
        
        
          nels and bridges.
        
        
          The 5 new tunnels at Derveni, Mavra Litharia,
        
        
          Akrata, Platanos and Panagopoula, will reduce
        
        
          travelling distances, noise and air pollution,
        
        
          also providing travellers with increased safety
        
        
          and comfort. Tunnelling work is complete in
        
        
          regard to the Panagopoula and Derveni tun-
        
        
          nels (two Corinth-bound tunnels), while a small
        
        
          section of the Mavra Litharia tunnels remains
        
        
          unfinished. Overall, tunnelling work is 62%
        
        
          complete.
        
        
          The recommencement of the project will lead
        
        
          to the construction of 120 kilometres of the
        
        
          Corinth-Patras section, with two lanes and an
        
        
          emergency lane per direction, and a Jersey
        
        
          barrier in the middle.
        
        
          Construction of the Patras-Pyrgos and
        
        
          Alpheios-Tsakona sections, with a total length
        
        
          of 164 kilometres, two lanes and an emer-
        
        
          gency lane per direction plus a Jersey barrier
        
        
          in the case of the former, and two lanes and a
        
        
          Jersey barrier in the case of the latter section,
        
        
          has been postponed to a later date.
        
        
          3) The Nea Odos concession, with a total length
        
        
          of 380 km, is divided into two main sections
        
        
          and includes the, 196 km long, “Ionia Odos”
        
        
          motorway, which stretches from the end of the
        
        
          “Harilaos Trikoupis” bridge at Antirion to
        
        
          Egnatia Odos, near Ioannina (interchange with
        
        
          the Egnatia Highway). The Ionia Odos section
        
        
          includes, among others, 24 bridges of single
        
        
          carriageway of an approximate length of 7.0
        
        
          km, as well as 4 tunnels of single carriageway
        
        
          of an approximate length of 11 km.
        
        
          It also includes a section of the PATHE motor-
        
        
          way, with a length of approximately 172.5 km,
        
        
          which stretches from the Metamorphosi inter-
        
        
          change (Attiki Odos area) to Skarfeia –after the
        
        
          town of Kammena Vourla– and the Schimatari-
        
        
          Chalkis connecting branch of PATHE, with a
        
        
          total length of 11 km.
        
        
          Almost all scheduled construction and upgrad-
        
        
          ing work on the PATHE motorway has been
        
        
          completed.
        
        
          4) The E65 road axis is the one beset with the
        
        
          worst delays. It includes the section that
        
        
          extends from the semi-junction with PATHE at
        
        
          Lamia to the interchange with Egnatia Odos
        
        
          (total length of 174 km), as well as the opera-
        
        
          tion of the PATHE section from Skarfeia to
        
        
          Raches.
        
        
          According to the deal reached between the gov-
        
        
          ernment and the concessionaire, the construc-
        
        
          tion of the Lamia-Xyniada junction section (32
        
        
          km) will be postponed to a future date, along with
        
        
          the next 64 km section (Trikala-Egnatia), for
        
        
          which a decision by the Council of State is still
        
        
          pending.
        
        